Case Study

Priors Inn Public House

Project timescale:
5 Weeks

Project Summary

  • 47.24 tons of general waste removed from site with a 98.8% recycling rate
  • 39.84 tons of wood left site with a 100% recycling rate
  • 5.78 tons of scrap metal left site with a 100% recycling rate
  • 1,134 man hours was used on this project