Case Study

Berth 9 Felixstowe Docks

Project timescale:
16 Weeks

Berth 9 - Felixstowe Docks
Project Value - TBC

On this project the Anglian team were contracted to break out and remove over 500m of Quay wall within Felixstowe Docks

Within this phase of works there was also over 700m of 1″ sheet piling to be burnt out and removed from site measuring 3m high

Whilst the demolition teams were kept busy the Earthworks team was contracted to move approximately 50,000 Tons of sand to a secondary location within the Docks

Project Summary

  • 611.29 Tons of Scrap Metal removed from site
  • Approximately 50,000 Tons of sand moved to another location on site